# Portfolios

> Group projects from every Space into portfolios and programmes, compare their traffic lights, phases and budgets, and see all of them on one Gantt.

A portfolio collects projects from any Space under one owner and one budget. The **Portfolios** page shows all of them in one table, with the traffic light from each project's [status report](/docs/projects/reports#status-reports), and on one Gantt chart. Use it to answer "which projects need management attention?" without opening each project.

<h2 id="hierarchy">
  How portfolios are structured
</h2>

A portfolio can sit under another portfolio. A portfolio with a parent is a programme. There is no limit to the depth.

```mermaid theme={"dark"}
flowchart TD
  P["Portfolio: Digital services"] --> G["Programme: Citizen portal"]
  P --> X["Project: Data platform"]
  G --> A["Project: Portal frontend"]
  G --> B["Project: Identity"]
  A --> W1["Work items"]
  B --> W2["Work items"]
  X --> W3["Work items"]
```

A project belongs to one portfolio at most. Deleting a portfolio keeps its projects and the portfolios below it; they lose this parent.

<h2 id="open">
  Open Portfolios
</h2>

Open **Portfolios** from the app drawer. Everyone who is signed in can see the portfolio tree.

<h2 id="overview">
  The Overview tab
</h2>

The top table is the portfolio tree:

| Column | Content |
| - | - |
| Name | The portfolio, with the portfolios below it |
| **Owner** | The person responsible |
| **Own budget** | The budget of this portfolio |
| **Including sub-portfolios** | Its budget plus all portfolios below it. Empty when the currencies differ |
| **Projects** | The number of projects |

The second table lists the projects:

| Column | Content |
| - | - |
| **Status** | The project status |
| **Phase** | The active [phase](/docs/projects/approvals) |
| **Traffic light** | From the latest approved status report, otherwise **No report yet** |
| **Management** | Whether the report asks for **Management attention** |
| **Next milestone** | The next open milestone |
| **Risks** | Open and critical risks from the [risk register](/docs/projects/risks) |
| **Budget used** | Turns orange from 80 % and red from 100 % |

Narrow the list with the portfolio filter (**All portfolios** or one portfolio with its sub-portfolios) and **Needs management only**.

<h2 id="gantt">
  The Gantt tab
</h2>

**Gantt** shows each portfolio and project as a summary row with its work items below. Projects without a portfolio are grouped under **Without portfolio**. Use **Open Gantt** on a row to open the chart for one portfolio.

* Narrow the chart with the chips above it. They work as on the [Board](/docs/projects/board#quick-filters) and load only the matching work items. When you open a single portfolio, its owner can click **Quick filters** to define named chips for it.
* Click **Columns** to choose which fields the left side shows. The choice is saved to your account.
* Zoom with **Day**, **Week**, **Month** or **Quarter**.
* Drag a work item bar to change its dates. Summary rows cannot be dragged.
* The chart shows up to 5,000 work items. Beyond that, open a single portfolio.

<Note>
  The portfolio Gantt draws no dependency arrows. See [Dependencies](/docs/planning/dependencies).
</Note>

<h2 id="manage">
  Create and manage portfolios
</h2>

<Steps>
  <Step title="Start a portfolio">
    Click **New portfolio**.
  </Step>

  <Step title="Fill in the form">
    Enter the **Name**, choose where it **Sits under** (or **Top level**), and add a **Description**, a **Budget** and its **Currency**.
  </Step>

  <Step title="Assign projects">
    In each project, open **Settings → Portfolio and budget** and choose the portfolio.
  </Step>
</Steps>

| Action | Who can do it |
| - | - |
| Create a top-level portfolio | A system administrator |
| Create, edit or delete a portfolio below | The owner of that portfolio or of any portfolio above it, and system administrators |
| Hand a portfolio to another owner | Someone who manages its parent |

<Note>
  The owner and the start and end dates of a portfolio cannot be set in the form today.
</Note>

## Related

<CardGroup cols={2}>
  <Card title="Planning overview" icon="map" href="/docs/planning/overview">
    Which planning tool answers which question.
  </Card>

  <Card title="Status reports" icon="file-chart-column" href="/docs/projects/reports#status-reports">
    Where the traffic light comes from.
  </Card>
</CardGroup>