# Risk register

> Record project risks in a Space's risk register, rate probability and impact on a 3 by 3 matrix, and link each risk to the work item that handles it.

The risk register lists what could go wrong in the projects of a Space, rated by probability and impact. Every risk sits on a 3 by 3 matrix, so the critical ones stand out. Each risk can name an owner, a project and the work item that handles it.

<h2 id="how-it-works">
  How it works
</h2>

Risks are [Registry](/docs/registry/overview) Objects. The register reads them from one Object Type and maps its fields to the roles it needs:

| Role | Required | Use |
| - | - | - |
| **Probability** | Yes | 1 to 3 |
| **Impact** | Yes | 1 to 3 |
| **Score** | No | Probability times impact |
| **Status** | No | The state of the risk |
| **Owner** | No | Who watches the risk |
| **Review date** | No | When to look at it again |
| **Project** | No | The project the risk belongs to |
| **Measure** | No | The work item that handles the risk |

<h2 id="set-up">
  Set up the register
</h2>

<Steps>
  <Step title="Switch on the module">
    In **Space Settings → Features**, switch on **Risks**.
  </Step>

  <Step title="Connect a schema">
    Open the Space's **Risks** page. Choose **Create from template**, which creates the Project Governance schema with risks, assumptions and decisions. Or accept the **Suggested connection** with **Connect**, or use **Map fields yourself** for a schema you already have.
  </Step>

  <Step title="Show risks in projects">
    In each project, switch on **Risks** under **Settings → Project features**. The project gets a **Risks** tab with its own risks. If the risk type has no project field yet, use **Add project field**.
  </Step>
</Steps>

<h2 id="matrix">
  Read the matrix
</h2>

| Score | Band |
| - | - |
| 1 to 2 | **Low** |
| 3 to 4 | **Medium** |
| 5 to 9 | **High**, counted as critical |

Risks without a rating are counted as **… unrated**. Filter the matrix with **All projects** or one project, and with **Critical only**. To re-rate a risk, drag it to another cell.

<h2 id="record">
  Record a risk
</h2>

<Steps>
  <Step title="Start">
    Click **Record risk**.
  </Step>

  <Step title="Describe and rate it">
    Enter the **Title** ("What could go wrong?"), choose probability and impact, and optionally the owner, the project and the measure.
  </Step>

  <Step title="Link the measure">
    For the measure, search for an existing work item and pick it. The risk then shows **Measure** with the work item key. Create the work item first if it does not exist yet.
  </Step>
</Steps>

Recording a risk needs contributor rights on the risk schema in the Registry and the right to edit work items in the Space.

<h2 id="troubleshooting">
  Troubleshooting
</h2>

| What you see | What to do |
| - | - |
| **No risk schema connected yet** | A Space manager connects a schema, see [Set up the register](#set-up) |
| **Recording risks needs contributor rights on the risk schema in the registry.** | Ask the schema's owner for contributor rights |
| **Risks are not tied to projects yet** | Use **Add project field**. It needs the editor right on the schema |

## Related

<CardGroup cols={2}>
  <Card title="Portfolios" icon="folder-tree" href="/docs/planning/portfolios">
    Open and critical risks per project.
  </Card>

  <Card title="Registry" icon="database" href="/docs/registry/overview">
    Where the risks are stored.
  </Card>
</CardGroup>