Dependency types
Dependencies created in Collabase are Finish to start: the blocked work starts when the blocking work is done.
Create a dependency
- On the Timeline
- In the work item
Drag from the dot at the end of one bar to another bar. See Timeline dependencies.
See dependencies
An arrow is drawn only when both work items are on the same timeline. A dependency on a work item in another project shows in Relations and in the Relation Graph, not as an arrow.
What Collabase does not do
- It does not move dependent work items when you reschedule the blocking one.
- It does not warn when a blocked work item starts before its blocker ends.
Critical path
Switch on Critical path in the Timeline toolbar to highlight the work items and arrows that set the finish date of the project. Hover a bar to see its slack in working days. Collabase reads the Blocks relations and their type and lag; work items without start or due date are left out. If the dependencies form a cycle, a note names the work items involved.Related