Skip to main content
A dependency records that one work item has to finish before another can proceed. In Collabase a dependency is a Blocks relation between two work items. It can connect work items in the same project or in different projects and Spaces.

Dependency types

Dependencies created in Collabase are Finish to start: the blocked work starts when the blocking work is done.

Create a dependency

Drag from the dot at the end of one bar to another bar. See Timeline dependencies.
Both ways need the Link task permission.

See dependencies

An arrow is drawn only when both work items are on the same timeline. A dependency on a work item in another project shows in Relations and in the Relation Graph, not as an arrow.

What Collabase does not do

  • It does not move dependent work items when you reschedule the blocking one.
  • It does not warn when a blocked work item starts before its blocker ends.
  • It has no critical path.
Check dependencies yourself after moving dates, for example with the Relation Graph.

Timeline

Draw and see dependencies in one project.

Work items

Relations and the relation graph.
Last modified on October 13, 2026